Which one is a product risk associated with the air quality management system?
A. The system required to monitor oxygen levels may be more expensive than those required to monitor air temperatures.
B. SubsInc may need to recruit extra developers and testers to deliver the project on time.
C. Oxygen levels may reach dangerously low levels.
D. Extreme temperatures may lead to heat exhaustion of personnel.
Which of the following is an accurate depiction of the hierarchy of test management documentation (where the highest comes first)?
A. Test policy-Test strategy-Project test plan-System test plan
B. Test strategy-Test policy-Project test plan-System test plan
C. Test policy-Project test plan-Test strategy-System test plan
D. Project test plan-Test strategy-System test plan-Test policy
Which of the following test design techniques would be most suitable for testing that the oxygen is released at the required times?
A. Decision Testing.
B. Statement Testing.
C. Data flow Testing.
D. Boundary Value Analysis.
When creating the functional specification for the temperature control system, which of the following review types would be most recommended to resolve any issues?
A. A walkthrough.
B. A technical review.
C. A management review.
D. A code inspection.
Which of the following best describes a testing challenge of the application domain of the routers described?
A. Testing that the receivers PC can store emails routed to it.
B. Testing that large organisations can scan incoming files routed to them for viruses.
C. Testing that packets are delivered by the routers in the required timescales.
D. Testing that files can be sent in any language.
When a software defect in a system has been found and fixed, which of the following activities should be undertaken next?
a.
Debugging.
b.
Confirmation testing.
c.
Regression testing.
d.
System testing.
e.
Static testing.
A.
a and b.
B.
b and c.
C.
c and d.
D.
c and e.
You are convinced that delivery will be late. Which of the following reviews would be recommended at this time?
A. A management review of the test plan and results.
B. A walkthrough of the test plan and results.
C. A technical review of the user-stories.
D. An inspection of all code for the trading environment.
At the end of Sprint 1, which of the following would give the best indication of test coverage?
A. Number of user-stories required to define the trading environment.
B. Amount of unit testing planned by developers for each user-story associated with the trading environment.
C. Number of links required to the stock exchange.
D. Percentage of user-stories tested and passed for the trading environment.
Which of the following provides the best example of a product risk leading to a project risk?
A. The signalling systems may have more defects than anticipated, leading to the need for more retesting to be carried out.
B. There may be unexpected lags on the network traffic communication, causing drivers to slow the trains down unnecessarily.
C. The new development staff may require training for this type of system, which, if not carried out, may lead to an increase in the number of defects introduced.
D. The budget may need to be increased significantly during the project, otherwise there may be delays in the delivery of the system.
Which two of the following measures would give the best indication of likely product quality?
a.
Number of hours of overtime worked.
b.
Number of test runs.
c.
Coverage of requirements achieved.
d.
Defect trends. e.Budget sent so far.
A.
a and c.
B.
b and d.
C.
c and d.
D.
a and d.