Which activity is not part of the Completion phase?
A. updating the testware to be preserved
B. assessing test results
C. evaluating the test process
D. selecting the testware to be preserved
The specification of test cases according to a test design technique follows five general steps. Which step is stablishing the starting point?Which step is ?stablishing the starting point?
A. step 2
B. step 3
C. step 4
D. step 5
See the illustration below:
Which test situations can be differentiated when the coverage type paths test depth level 2 is used?
A. 1-2; 2-3; 3-4; 2-4; 2-5; 2-6; 3-5; 3-6; 4-5; 4-6; 5-6
B. 1-2; 1-3; 1-4; 2-5; 3-5; 4-5; 2-6; 3-6; 4-6
C. 1-2-5; 1-2-6; 1-3-6; 1-3-5; 1-4-6; 1-4-5
See the illustration below:
What is the minimum number of logical test cases generated by the use of the Process Cycle Test if the coverage type paths test depth level 2 is used?
A. 3
B. 5
C. 6
D. 9
What is not one of the aims of the 'testability review test basis' report?
A. providing feedback on the quality of the test basis and its impact on the planned test procedure
B. gaining an insight into the estimation for the test procedure
C. obtaining information on project risks
D. discussing the weak spots in the system design on time
With which units do you best start the unit integration test?
A. the units that are ready first
B. the units that are the worst (least) documented
C. the units in which the most problems are expected
What constitutes a good test environment?
A. it is possible to adequately determine to what extent the test object meets the requirements
B. it has been configured and tested by qualified personnel
C. it meets both of the requirements listed above
D. it is as similar to the production environment as possible and the test data is consistent
See the procedure flow below:
How many test situations are produced when the coverage type paths with test depth level 2 is used?
A. 3
B. 8
C. 12
D. 13
What is the correct description of the term est level?
A. the information that defines the required system behavior
B. a group of test activities with the attention of checking the information system in respect of a number of correlated (part aspects of) quality characteristics
C. a group of test activities that are managed and executed collectively
During which TMap phase is testing 'dynamic implicit'?
A. Specification
B. Execution
C. Preparation