Sensitivity analysis is typically displayed as a/an:
A. Decision tree diagram.
B. Tornado diagram.
C. Pareto diagram.
D. Ishikawa diagram.
Which of the following describes the similarities of the process groups and project life cycle?
A. The life cycle involves three project management process groups
B. Both provide a basic framework to manage the project
C. Each project must have a life cycle and all processes in the five process groups
D. The project life cycle is managed by executing the processes within the five process groups
What is a tailoring consideration for Project Scope Management?
A. Life cycle approach
B. Continuous improvement
C. Validation and control
D. Project complexity
In Project Resource Management, which process uses recognition and rewards as a tool and technique?
A. Control Resources
B. Develop Team
C. Manage Team
D. Monitor Team
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is using the project manager?
A. Three-point estimating
B. Parametric estimating
C. Bottom-up estimating
D. Data analysis
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
A. Identify Stakeholders
B. Plan Stakeholder Engagement
C. Manage Stakeholder Engagement
D. Monitor Slakeholder Engagement
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
A. Schedule
B. Quality
C. Communications
D. Cost
After Define Activities and Sequence Activities, the next process is:
A. Estimate Activity Resources.
B. Estimate Activity Durations.
C. Develop Schedule.
D. Control Schedule.
Which of the following factors is lowest at the start of the project?
A. Cost of changes
B. Stakeholder influences
C. Risk
D. Uncertainty
The scope of a project cannot be defined without some basic understanding of how to create the specified:
A. objectives
B. schedule
C. product
D. approach