Select the true statement regarding Portfolio Scenarios.
A. You can add user access to the Portfolio Scenario from waterline analysis.
B. You can save the Waterline Analysis as a new scenario.
C. You can update individual project status from the Waterline Analysis/Scenario.
D. You can create a new portfolio from the Waterline Analysis.
What takes the highest precedence during Resource Leveling?
A. Leveling priority
B. Mandatory constraint
C. Topological sequent
D. Resource Calendar
Where are tolerances set in Primavera P6 EPPM?
A. in Performance Thresholds
B. in Global Preferences
C. in Performance Status tab
D. in Portfolios
Select the true statement regarding Role proficiency.
A. The numbers and values can be customized.
B. User Defined Fields can be substituted for numbers and values.
C. The numbers and values cannot be customized.
D. Global Resource Codes can be substituted for numbers and values.
In addition to the four primary elements that comprise security, what additional feature in P6 Web will determine a user's access to data?
A. Portfolio Portlets
B. User Dashboards
C. User Interface View
D. Resources portlets
Identify the best definition of Funding Source.
A. Contributing source of funds for a project's financing are assigned in Project Details
B. Percentage of the total fund allocated to the project are created and managed at the Project level
C. Agency where funds will be allocated for the project
D. Removes unwanted portlets from the User Interface View
Select three functions available in P6 EPPM Web Portfolios that will allow a Portfolio Manager to analyzeand prioritize projectsintheir portfolio.
A. Waterline
B. Add Project
C. Copy Project
D. Bubble Chart
E. Create spreadsheet
F. Scorecard
G. Modify Project
Select the true statement regarding Global Change.
A. Global change can be executed by any user.
B. Global change can modify Global Codes.
C. Global change can modify Global Security Profiles.
D. Global Change can replace existing project data with new data.
Select two true statements regarding Calendars.
A. Global Calendars are available to a subset of projects.
B. Project Calendars are available for the current project only.
C. Only a limited number of calendars can be created.
D. Resource calendars are applied to all Resources with the same Primary Role.
E. Activity type determines whether the activity uses Resource Calendars for scheduling.
F. Activity Calendars are managed by individual Resources.
Select the true statement regarding summarized data and Primavera Web.
A. Live data is used for Resource management.
B. Live data is used for Portfolio management.
C. Summarized data is used for Resource management.
D. Summarized data is used for Project management.