Identify two true statements regarding the rolling up of data within a Work Breakdown Structure (WBS).
A. Actual Data rolls up to a Parent level.
B. Actual Data rolls up to a Portfolio level.
C. Actual Data rolls up to a Resource level.
D. Actual Data rolls up to Program level
E. Actual Data rolls up to a Project level.
Your customer is attempting to implement Resource Capacity Planning using Roles. The Roles Dictionaryhas been set up by Location, so that Human Resources Is able to determine projected RoleshortagesLocation. The customer's projects are 20 yearsinduration.
What limitation of Resource Capacity Planning may create an issue for the customer?
A. Roles cannot be used in Capacity Planning.
B. Resources cannot be assigned at the Project level.
C. Staffing analysis can be used to forecast only up to 10 years in the future.
D. Role view is governed by Responsible Manager assignments.
Identify the impact of deleting a resource from the Resource Breakdown Structure?
A. Allactualand remaining work are removed from the database.
B. Costs for pastprojects would not be affected as theactualhave already been recorded In the database.
C. Budgets for future projects would be removed from the database.
D. Budgets from past projects would be removed from the database.
E. Costs for past projects would be reduced because the cost associated with the resource is deleted.