What is copied when transferring a simulation version back to an operative project? There are 3 correct
answers to this question.
Response:
A. Plan costs
B. WBS elements
C. Actual work
D. Maintenance orders assigned to the project
E. Network activities
What are the different views available for capacity planning and work center planning? There are 2 correct
answers to this question.
Response:
A. Work center view
B. Capacity planning view
C. Periodic view
D. Project view
What do you choose when creating a new network by copying an operative network? There are 3 correct
answers to this question.
Response:
A. PS texts
B. Relationships
C. Milestones
D. WBS elements
Response:
A. With partial confirmations of the activity
B. By transferring the working times for the activity that was entered in CATS (Cross-Application Time Sheet)
C. With the period-end closing
D. By setting the status locked account assignment
E. With the final confirmation of the activity
What are the three tables that are defined for order type in network costing? There are 3 correct answers
to this question.
Response:
A. Each order type
B. Each order type and plant
C. Network profile
D. Each plant
What do you use in the parameters for network type to specify whether a workflow is to be generated in
the case of purchase order relevant change? Please choose the correct answer.
Response:
A. Workflow indicator
B. Workflow purchase order change indicator
C. Workflow change indicator
D. Purchase order change indicator
Which of the following can be used to calculate and update interest in SAP project system? There are 2
correct answers to this question.
Response:
A. Planned interest calculation
B. Actual interest calculation
C. Compound interest calculation
D. Result analysis
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how? Please choose the correct answer.
A. MRP groups
B. Automatic requirement grouping indictor
C. MRP element indicator
D. lVIateriaI group
Which of the following can be derived automatically when you carry out scheduling in projects with
networks? There are 2 correct answers to this question.
Response:
A. Activity dates
B. WBS element dates
C. Network dates
D. Scheduling dates
While customizing the progress tracking profile which indicator specifies whether the respective dates are
to be scheduled?
Please choose the correct answer.
Response:
A. Scheduling forwards
B. Scheduling backwards
C. Variances
D. Scheduling baseline, planned and forecast