Which of the following statements about consumption are correct? (Choose two)
A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
B. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
C. Consumption is restructured with the planning run.
D. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
A. Interactive single-item planning for the delayed assembly
B. Multi-level single-item planning with the "simulation mode" option
C. Total planning online
D. Multi-level single-item planning with the "display material list" option
What could be a consequence of the confirmation of an operation?
A. Settlement of the actual costs
B. Reduction of capacity requirements
C. Rescheduling of the production order
D. Update of the planned costs
What master data do you need for material replenishment using the KANBAN procedure? (Choose two)
A. Production supply area
B. Product cost collector
C. Rate routing
D. Production version
E. Control cycle
Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
A. Lead time scheduling cannot take place.
B. Requirements planning creates an appropriate exception message in basic dates scheduling.
C. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
D. Dependent requirements request the components from the bill of materials at wrong times when using basic dates scheduling.
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation.
What can be the origin of the formula parameters used for scheduling? (Choose three)
A. Standard values in the operations of routings
B. General operation values of routings
C. General values from work scheduling view of the material master
D. User-defined fields in the operation of routings
E. General item values of bill of materials
Which of the following statements regarding lot size procedures is correct?
A. The lot size quantity can be influenced using a minimum lot size and the rounding profile.
B. If a make-to-order production strategy is used, only the lot-for-lot (exact) lot size can be applied.
C. If a long-term lot size is used, procurement is conducted with a long-term perspective.
D. The procurement quantity of a lot size procedure can be specified using a safety time period profile.
A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.
Which of the following statements are true for the two lists at this stage? (Choose two)
A. The MRP list displays the production order.
B. The stock/requirements list displays the production order.
C. The stock/requirements list was updated at the precise time it was accessed.
D. The MRP list has the status "processed".
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
A. Set "Container in transport"
B. Set "Container empty"
C. Set "Container full"
D. Set "Container in process"
Which of the following master data can be used with process orders? (Choose three)
A. Serial numbers
B. Production versions
C. Resources
D. Master recipies
E. Production/resource tools