A team finds bugs in a feature. What is the best action to take?
A. Create a task "Correct bugs" and estimate it.
B. Create a task "Correct bugs" and let the Product Owner prioritize it.
C. Create a User Story "As a client I want a zero defect product" and estimate it.
D. Create a User Story "As a client I want a zero defect product" and let the Product Owner prioritize it.
A team's physical environment can have a big influence on how Agile a team can become.
An important benefit of an open space workplace is the ease with which the layout of the area can be
changed.
Why does this comply with the Agile principles?
A. It follows the inspect and adapt cycle, as the people on the team are learning how to work best with one another during the process.
B. Pair programming is only possible in an open environment.
C. Self-organization is only possible in an open space environment.
D. With people involved, there will always be people issues. Open work spaces allow the Scrum Master to detect people issues and resolve them.
What is the difference between NPV and IRR?
A. NPV is a measure of how much money a project can be expected to return in future value. IRR is a measure of how quickly the money invested in the project will decrease in value.
B. NPV is a measure of how much money a project can be expected to return in today's present value. IRR is a measure of how quickly the money invested in the project will increase in value.
C. IRR is a measure of how much money a project can be expected to return in future value. NPV is a measure of how quickly the money invested in the project will decrease in value.
D. IRR is a measure of how much money a project can be expected to return in today's present value. NPV is a measure of how quickly the money invested in the project will increase in value.
Which information Radiator can the team use best during the Sprint to track the work?
A. Gantt chart
B. Product Backlog
C. Release Burn Up
D. Task board
A company is already using Scrum very successfully within the development department. While highly effective Scrum Teams deliver new software increments quickly, these increments are not being delivered fast enough to customers. Releases happen once every 3 months and it takes too much effort to make sure that the releases go smoothly.
What type of framework should this company try to establish?
A. DevOps
B. DSDM
C. Lean
D. Waterfall
How can pair programming help with adopting Agile?
A. It helps recognizing who wrote which code
B. It is beneficial to knowledge transfer
C. It makes development faster and cheaper
After the creation of the Release Plan, the Product Owner says:
Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.
The Scrum Master argues that the end date of the release can be positively or negatively impacted by
three factors. Completed work is the first factor.
What are the other two factors?
A. Changed requirements and estimation mode
B. Changed requirements and revised estimates
C. Fixed requirements and estimation mode
D. Fixed requirements and revised estimates
When two companies merge, there is often a lack of communication and transparency between locations. What can best be done to reduce the risk of full-scale blow-ups between locations?
A. Establish the `connector role' within the team
B. Establish collaborating collocated teams
C. Establish deliberately collocated teams
D. Establish deliberately distributed teams
Company X-AppGo is very interested in getting the benefits of both the ITIL®Framework and the Agile principles. They want to establish a disciplined service based approach, while reducing lead team in releasing application enhancements and improvements to their customer base.
Based on the above scenario, which would be the best processes to start integrating Agile into the ITIL® Framework?
A. Service Design and Service Transition
B. Service Strategy and Service Design
C. Service Strategy and Service Operation
D. Service Transition and Service Operation
The Scrum-of-Scrums meeting is designed to allow clusters of Scrum Teams to discuss their work, focusing especially on areas of overlap and integration.
Who should attend the Scrum-of-Scrum meetings on behalf of your Scrum Team?
A. The Product Owner
B. The Scrum Master
C. The team can choose anyone
D. The whole team