You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?
A. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning
B. Demand management -> Sales and operations planning -> Capacity planning -> Long- term planning > Material requirements planning
C. Material requirements planning -> Demand management -> Sales and operations planning -> Longterm planning -> Capacity planning
D. Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).
Which of the following properties for the resulting dependent requirements applies?
A. In multi-level backward scheduling, dependent requirements are calculated to the exact second.
B. If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.
C. When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.
D. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.
You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.
How can you fulfill these requirements in SAP ECC? (Choose two)
A. Use strategy 50 (planning without final assembly) for the finished product and no strategy for all assemblies in the bill of material.
B. Use strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
C. Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
D. Use strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
Which of the following elements do you have to prepare for costing of a production order to function without errors? (Choose three.)
A. Assign costing variants to order type.
B. Propose a standard text key in work center.
C. Assign a production scheduling profile to the material master (product).
D. Enter formulas for costing in the work center.
E. Use an operation control key with the indicator costing-relevant.
During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system.
Which of the following procurement type properties are valid? (Choose two)
A. If both procurement types are allowed with entry X (both procurement types), requirements planning assumes in-house production.
B. Procurement types E (in-house production) and F (external procurement) always have to be further refined with special procurement types.
C. Procurement types E (in-house production), F (external procurement), or X (both procurement types) can be selected for a material independent of the material type.
D. If procurement type E (in-house production) is set, external procurement may still be possible, depending on the material type.
What could be a consequence of the confirmation of an operation?
A. Settlement of the actual costs
B. Reduction of capacity requirements
C. Rescheduling of the production order
D. Update of the planned costs
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
A. Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.
B. Activate the availability check and assign an overall profile in the checking control of the order type / plant combination.
C. Assign an appropriate availability checking rule to the material master for the product.
D. Activate the availability check and assign an overall profile in the production scheduling profile.
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation.
What can be the origin of the formula parameters used for scheduling? (Choose three)
A. User-defined fields in the operation of routings
B. General operation values of routings
C. General item values of bill of materials
D. General values from work scheduling view of the material master
E. Standard values in the operations of routings
Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)
A. Batch size optimization
B. Midpoint scheduling
C. Lot size optimization
D. Finite capacity scheduling
E. Setup time reduction
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials by default. However, some materials need to have a different planning horizon.
Which procedure do you recommend for setting the planning horizon?
A. Set the planning horizon in the MRP groups in Customizing and store deviant entries in the material masters for the corresponding materials.
B. Set the planning horizon in the plant parameters in Customizing and store deviant entries in the material masters for corresponding materials.
C. Set the planning horizon in the MRP groups and assign deviant entries via the plant parameter settings in Customizing.
D. Set the planning horizon in the plant parameters in Customizing and assign deviant entries via the MRP groups for the corresponding materials.