A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
A. RFI
B. RACI
C. WBS
D. SOW
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly.
Which of the following should have been considered during initial planning to prevent this situation?
A. ESG
B. PHI
C. PII
D. ROI
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
A. External
B. Internal
C. Mandatory
D. Discretionary
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
A. Gantt chart
B. Maintenance window schedule
C. Functional requirements
D. Test results
A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?
A. Resource allocation
B. Communication security
C. Technological factors
D. Cultural differences
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
A. Scope creep
B. Collecting requirements
C. Decision-making
D. Project change
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
A. Smoke testing
B. Regression testing
C. Unit testing
D. User acceptance testing
A portfolio manager needs to provide the senior management team with a dynamic, high-level, monthly status update on all active projects in the portfolio. Which of the following should the manager use to accomplish this task?
A. Dashboard
B. Status report
C. Gantt chart
D. Email
Which of the following would be the MOST beneficial to determine whether a project has met the defined objectives?
A. Schedule variance
B. Cost variance
C. Work breakdown structure
D. Key performance indicators
Which of the following are characteristics of a project? (Choose two.)
A. Ongoing
B. Temporary
C. Start and finish
D. Achieving a goal
E. Consisting of milestones
F. Restricting the budget