Want to pass your PMI Agile Certified Practitioner (PMI-ACP)® PMI-ACP exam in the very first attempt? Try Pass2lead! It is equally effective for both starters and IT professionals.
VCE
An Agile team expects a velocity of 8. During sprint planning, the stories were estimatedand prioritized in the following order:
Story A_4Story Points Story B_2Story Points Story C_3 Story Points Story D_2Story Points
Which stories should the team include in Sprint 1, without splitting the stories?
A. Stories A, C, and D
B. Stories A, B, and C
C. Stories A, B, and D
D. Stories B, C, and D
What role should a servant leader perform to reduce team distractions and improve progress toward project goals?
A. Managing: To ensure compliance with the project plan
B. Mentoring: To share their knowledge with the team
C. Controlling: To ensure compliance with the scope, budget, and schedule
D. Auditing: To ensure adherence to organizational compliance policies
A company is considering developing a new, complex application that will require a large initial investment. However, if successful, the profit potential is high.
When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?
A. Calculated planned percent complete (PPC)
B. Many small minimally marketable features (MMFs)
C. Story points rather than cost estimates
D. Calculated earned value (EV)