Want to pass your Project Management Professional - 2024 New Version PMP exam in the very first attempt? Try Pass2lead! It is equally effective for both starters and IT professionals.
VCE
A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion What two actions should the project manager take? (Choose two)
A. Contact the team member's functional manager and invite them to the next retrospective
B. Meet with the entire team to review the ground rules about safe environments
C. Meet with the product owner to talk about the situation.
D. Contact the team member to explain what information can be shared outside the team
E. Meet with the sponsor to review the situation.
An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.
What should the project manager do?
A. Add 4 additional weeks to the schedule and request additional resources.
B. Ask the sponsor to obtain a special work permit to continue work.
C. Review the project management plan to see the impact of the possible delay.
D. Crash the resource management plan to keep the schedule on track.
A project manager is tasked with developing a coaching model to support and recognize team members' growth.
What should the project manager consider when defining their coaching strategy?
A. Established patterns of communication
B. Organization's strategic goals
C. Individual and personal objectives
D. Project team's shared objectives