Want to pass your SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing C_TS422_2021 exam in the very first attempt? Try Pass2lead! It is equally effective for both starters and IT professionals.
VCE
What is the purpose of collective orders?
A. To manage production orders for an entire finished product on multiple levels
B. To post any component withdrawal as single backflush with order confiramtion
C. To post production costs on a cost collector instead of the production order
D. To combine order management of co-products any by-products with the main product.
In the Schedule Production app which setting can you make for the planning strategy?
A. Fitness level
B. Scheduling control
C. Fixed pegging
D. Direction
E. Planning mode
You set up a material as a phantom assembly by entering the special procurement key in the material master.
How can you switch off the phantom assembly in a specific bill of material (BOM)?
A. Change the special procurement key of the phantom assembly in the BOM.
B. Change the explosion type of the phantom assembly in the BOM.
C. Change the phantom item indicator for the phantom assembly in the BOM.
D. Change the item category of the phantom assembly in the BOM.